2025 Xi’an Brictec KTB Project Latest Progress
In 2025, Xi’an Brictec will launch its second major engineering project in Iraq — the KTB sintered brick production line. The project plans to build three modern tunnel kiln sintered brick production lines, to be advanced in three phases. After the completion of Phase I and Phase II, the total daily output is expected to reach 900 tons, mainly producing clay sintered bricks with the specification of 240*115*75mm, 400*200*200mm, 200*400*200mm. This project not only consolidates Xi’an Brictec’s leading position in the Middle Eastern market but also provides strong technical support for the upgrading and transformation of Iraq’s building materials industry.
Latest construction progress as of August 2025:
Third batch of goods arrived at the site
Tunnel kiln masonry construction
250T kiln wall construction at the discharge end
650T kiln foundation pit construction
Retaining wall construction for Chenhua warehouse
V-shaped foundation construction for Chenhua warehouse commenced
Copyright Notice:
All images are sourced from Brictec Iraq project site photography. Unauthorized use will be pursued for legal liability.
Edited by: JF & Lou